Fugar & Agyakwah-Baah (2010)Fugar, F. D. K., & Agyakwah-Baah, A. B. (2010). Delays in building construction projects in Ghana. The Australasian Journal of Construction Economics and Building, 10(1), 103-116. http://dx.doi.org/10.5130/ajceb.v10i1/2.1592. http://dx.doi.org/10.5130/ajceb.v10i1/2....
|
Ghana |
32 |
Delay on payments |
RII |
130 |
Naoum (2016)Naoum, S. G. (2016). Factors influencing labor productivity on construction sites: A state-of-the-art literature review and a survey. International Journal of Productivity and Performance Management, 65(3), 401-421. http://dx.doi.org/10.1108/IJPPM-03-2015-0045. http://dx.doi.org/10.1108/IJPPM-03-2015-...
|
|
46 |
Inefficient project planning in the pre-construction phase |
RII |
36 |
Doloi et al. (2012)Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), 479-489. http://dx.doi.org/10.1016/j.ijproman.2011.10.004. http://dx.doi.org/10.1016/j.ijproman.201...
|
India |
45 |
Lack of commitment |
RII |
77 |
Sambasivan e Soon (2007)Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517-526. http://dx.doi.org/10.1016/j.ijproman.2006.11.007. http://dx.doi.org/10.1016/j.ijproman.200...
|
Malaysia |
28 |
Precarious management from the constructor |
RII |
150 |
Aiyetan et al. (2011)Aiyetan, A., Smallwood, J., & Shakantu, W. (2011). A systems thinking approach to eliminate delays on building construction projects in South Africa. Acta Structilia, 18(2), 19-39.
|
South Africa |
7 |
Construction planning and control techniques |
Mean Score |
112 |
Kaming et al. (1997)Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15(1), 83-94. http://dx.doi.org/10.1080/014461997373132. http://dx.doi.org/10.1080/01446199737313...
|
Indonesia |
11 |
Changes in the project |
Severity index |
31 |
Lo et al. (2006)Lo, T. Y., Fung, I. W. H., & Tung, K. C. F. (2006). Construction delays in Hong Kong civil engineering projects. Journal of Construction Engineering and Management, 132(6), 636-649. http://dx.doi.org/10.1061/(ASCE)0733-9364(2006)132:6(636). http://dx.doi.org/10.1061/(ASCE)0733-936...
|
China (Hong Kong) |
30 |
Inadequate facilities or financial difficulties of the constructor |
Overall Mean Score |
158 |
Gardezi et al. (2014)Gardezi, S. S. S., Manarvi, I. A., & Gardezi, S. J. S. (2014). Time extension factors in construction industry of Pakistan. Procedia Engineering, 77(1), 196-204. http://dx.doi.org/10.1016/j.proeng.2014.07.022. http://dx.doi.org/10.1016/j.proeng.2014....
|
Pakistan |
27 |
Legal and order matters |
RII |
50 |
Kazaz et al. (2012)Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012). Causes of delays in construction projects in Turkey. Journal of Civil Engineering and Management, 18(3), 426-435. http://dx.doi.org/10.3846/13923730.2012.698913. http://dx.doi.org/10.3846/13923730.2012....
|
Turkey |
34 |
Changes in the materials of the project |
RII |
71 |
Aibinu & Odeyinka (2006) |
Nigeria |
44 |
Financial difficulties of the constructor |
RII |
102 |
Toor and Ogunlana (2008)Toor, S., & Ogunlana, S. O. (2008). Problems causing delays in major construction projects in Thailand. Construction Management and Economics, 26(4), 395-408. http://dx.doi.org/10.1080/01446190801905406. http://dx.doi.org/10.1080/01446190801905...
|
Thailand |
75 |
Lack of standard in the projects |
Mean Score |
76 |
Mezher & Tawil (1998)Mezher, T. M., & Tawil, W. (1998). Causes of delays in the construction industry in Lebanon. Engineering, Construction, and Architectural Management, 5(3), 252-260. http://dx.doi.org/10.1108/eb021079. http://dx.doi.org/10.1108/eb021079...
|
Lebanon |
64 |
Financing and outsourcing schedule, contractual relations and project changes, inadequate planning. |
Importance Index |
36 |
Faridi & El-Sayegh (2006)Faridi, A. S., & El-Sayegh, S. M. (2006). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), 1167-1176. http://dx.doi.org/10.1080/01446190600827033. http://dx.doi.org/10.1080/01446190600827...
|
Arab Emirates |
44 |
Inadequate initial planning of project and delay in project preparation and approval |
RII |
93 |
Assaf & Al-Hejji (2006)Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-357. http://dx.doi.org/10.1016/j.ijproman.2005.11.010. http://dx.doi.org/10.1016/j.ijproman.200...
|
Saudi Arabia |
73 |
Change of requests from the contractor during the construction process |
Severity, Frequency e Importance Index |
54 |
Sweis et al. (2008)Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008). Delays in construction projects: the case of Jordan. International Journal of Project Management, 14(3), 665-674. http://dx.doi.org/10.1016/j.ijproman.2007.09.009. http://dx.doi.org/10.1016/j.ijproman.200...
|
Jordanian |
91 |
Financial difficulties of the constructor and changes in the projects |
Drewin’s Open Conversion System |
40 |
Le-Hoai et al. (2008)Le-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008). Delay and cost overruns in Vietnam large construction projects: a comparison with other selected countries. KSCE Journal of Civil Engineering, 12(6), 367-377. http://dx.doi.org/10.1007/s12205-008-0367-7. http://dx.doi.org/10.1007/s12205-008-036...
|
Vietnam |
87 |
Lack of supervision and management of the construction site |
Severity, Frequency e Importance Index |
21 |