Acessibilidade / Reportar erro

Algoritmo de programação de máquinas individuais com penalidades distintas de adiantamento e atraso

In this work we consider the one machine problem, with distinct due-dates and penalties for earliness and tardiness. For a previously defined sequence, we utilize the sum of weighted lateness (earliness or tardiness) as objective function. This work is presented as a generalization of the Garey et al. (1988) scheduling algorithm. Using a computational structure called heap, this algorithm allows a schedule construction in O(nlogn) time while the best found in literature runs in O(n²).

production scheduling; idle time insertion; JIT scheduling


Sociedade Brasileira de Pesquisa Operacional Rua Mayrink Veiga, 32 - sala 601 - Centro, 20090-050 Rio de Janeiro RJ - Brasil, Tel.: +55 21 2263-0499, Fax: +55 21 2263-0501 - Rio de Janeiro - RJ - Brazil
E-mail: sobrapo@sobrapo.org.br