Analyzing key success factors in public-private partnership BOT projects: an empirical study on financing influences, insights, and analysis in construction management

ABSTRACT

The study encompasses various infrastructural amenities such as railways, roads, ports, bridges, tunnels, power plants, hospitals, municipal buildings, and other public-use facilities, which are essential for every country’s economic growth. Recognizing the challenges faced by governments in independently providing all infrastructure components, Public Private Partnerships [PPPs] have emerged as a cooperative approach between the public and private sectors. This paper explores the risks, delays, key success factors, contractor selection, and best value selection models in construction project management. In addition, the paper emphasizes the challenges that governments need to address in order to ensure the efficient functioning of the BOT (Built Operate Transfer) network. The challenges in establishing an efficient BOT network are highlighted, and a decision-support system using the .Net framework is developed to aid in the prequalification and rating of BOT marketers. The purpose of this system is to provide the best value to the public procurer by employing regression analysis to rate bidders/applicants and utilizing a composite programming method based on relative weighting.

Keywords
Infrastructure Development; Public-Private Partnerships; Construction Project Management; Risk Assessment; Prequalification Process

1. INTRODUCTION

The country’s economic development depends on its civil infrastructure. Infrastructure may be viewed as the foundation upon which society is constructed. Highways, railways, ports, bridges, hydraulic structures, power plants, tunnels, municipal infrastructure including sanitation and water supply, and other public-use amenities all fall under this category. Building and maintaining essential infrastructure requires long-term financial commitment. The use of innovative finance has been spurred by the urgent demand for such projects, as well as recurring budgetary deficits faced by government agencies [1[1] KARTAM, N.A., KARTAM, S.A., “Risk and its management in the Kuwaiti construction industry: a contractors’ perspective”, International Journal of Project Management, v. 19, n. 6, pp. 325–335, 2001. doi: http://doi.org/10.1016/S0263-7863(00)00014-4.
https://doi.org/10.1016/S0263-7863(00)00...
]. Due to a lack of national fund, many governments, particularly those in developing countries, have asked private sector groups to participate in long-term contractual arrangements for the funding, building, and operation of capital-intensive infrastructure projects. India’s transportation and urban development have seen the most significant growth. This boom is largely driven by a surge in infrastructure projects, especially in terms of project quantity [2[2] ABEDNEGO, M.P., OGUNLANA, S.O., “Good project governance for proper risk allocation in public–private partnerships in Indonesia”, International Journal of Project Management, v. 24, n. 7, pp. 622–634, 2006. doi: http://doi.org/10.1016/j.ijproman.2006.07.010.
https://doi.org/10.1016/j.ijproman.2006....
]. Public-private partnerships (PPP) are seen as crucial for maintaining India’s economic growth above 6% annually, considering the limitations of the existing infrastructure. The Government of India (GoI) has undertaken attempts in recent years to increase infrastructure investment, notably to catalyze more private participation [3[3] ADNAN, H., RAHMAT, M.N., FATANAH, N., et al., “Risk management assessment for partnering projects in the Malaysian Construction Industry”, Journal of Politics and Law, v. 1, n. 1, pp. 76–81, 2008. doi: http://doi.org/10.5539/jpl.v1n1p76.
https://doi.org/10.5539/jpl.v1n1p76...
]. Infrastructure development, on the other hand, usually necessitates a large upfront financial commitment due to the significant capital expenditure necessary during the building stage [4[4] ALGAHTANY, M., ALHAMMADI, Y., KASHIWAGI, D., “Introducing a new risk management model to the Saudi Arabian construction industry”, Procedia Engineering, v. 145, pp. 940–947, 2016. doi: http://doi.org/10.1016/j.proeng.2016.04.122.
https://doi.org/10.1016/j.proeng.2016.04...
]. Infrastructure projects are fraught with dangers that might result in cost overruns and lower financial returns. The source says that about 1000 infrastructure projects are backlogged among 27% of central government projects, while about 15% have exceeded their initial cost projections [5[5] ABD KARIM, N.A., RAHMAN, I.A., MEMMON, A.H., et al., “Significant risk factors in construction projects: Contractor’s perception”, In: 2012 IEEE Colloquium on Humanities, Science and Engineering (CHUSER), pp. 347–350, Kota Kinabalu, Malaysia, 2012. doi: http://doi.org/10.1109/CHUSER.2012.6504337.
https://doi.org/10.1109/CHUSER.2012.6504...
]. As a result, raising and arranging capital for building infrastructure is a difficult task. The infrastructure funding needs of India vary from US$ 1 to US$ 3 trillion each year. States with high population densities, such as Uttar Pradesh, Maharashtra and Bihar, as well as the Eastern area which has a lower population density and steep terrain, are expected to have greater infrastructure requirements. Demand is also anticipated to be driven by infrastructure geared for climate adaptation and adopting smart technology-based solutions. To address the rising infrastructure deficits in the medium term, new sources and methods of finance must be opened [6[6] KANDASAMY, Y., THANGAVEL, B., SUKUMAR, K.K., et al., “Strength properties of engineered cementitious composites containing pond ash and steel fiber”, Matéria (Rio de Janeiro), v. 29, n. 1, pp. e20230277, 2024. doi: http://doi.org/10.1590/1517-7076-rmat-2023-0277.
https://doi.org/10.1590/1517-7076-rmat-2...
].

These are three important critical areas that should be considered for effective management:

  • (i)

    Accelerating public-private partnerships (PPPs)

  • (ii)

    Increasing investments in smart infrastructure solutions; and

  • (iii)

    Creating capacity through a “learning-by-doing” strategy to improve infrastructure finance usage.

A Public-Private Partnership (PPP) Project means a project based on an agreement or special privileges contract between a government or statutory entity on the one hand and a private sector company on the other hand, for delivering an infrastructure service on payment of user charges,” according to the Government of India’s Strategy for Economic Assistance to PPP (Public Private Partnerships) in Infrastructure [7[7] ASSAF, S.A., AL-HEJJI, S., “Causes of delay in large construction projects”, International Journal of Project Management, v. 24, n. 4, pp. 349–357, 2006. doi: http://doi.org/10.1016/j.ijproman.2005.11.010.
https://doi.org/10.1016/j.ijproman.2005....
]. There is no generally accepted definition of a public-private partnership (PPP). PPPs are long-term contractual collaborations between public and private sector entities, with the goal of funding, developing, constructing, and running infrastructure facilities and services that are previously supplied by the government [8[8] GOH, C.S., ABDUL-RAHMAN, H., “The identification and management of major risks in the Malaysian construction industry”, Journal of Construction in Developing Countries, v. 18, n. 1, pp. 19–32, 2013.]. In a Public-Private Partnership (PPP), both participating partners agree to work together to execute, operate, and manage the project. This collaboration is typically formalized through legally binding contracts or other agreed-upon methods [9[9] ZHANG, T., WANG, B., LU, X., et al., “Flexural properties of textile-reinforced concrete with nonorthogonal grids”, Polymers, v. 14, n. 23, pp. 5185, 2022. doi: http://doi.org/10.3390/polym14235185. PMid:36501580.
https://doi.org/10.3390/polym14235185...
]. The partnership is established based on the unique skills and expertise of each partner, with the primary objective of meeting specific public requirements by allocating: Incomes, Jeopardies, Recompences, and Responsibilities [10[10] YOU, J., PARK, J., PARK, S.-K., et al., “Experimental study on the flexural behavior of steel-textile-reinforced concrete: various textile reinforcement details”, Applied Sciences (Basel, Switzerland), v. 10, n. 4, pp. 1425, 2020. doi: http://doi.org/10.3390/app10041425.
https://doi.org/10.3390/app10041425...
]. These and other aspects of PPP projects, such as implementation details, termination, liabilities, dispute resolution, and payment arrangements, are negotiated and written in formal service contracts signed by all parties involved [11[11] KIM, S.H., LEE, S.H., “Study on flexural strength of textile-reinforced mortar panel with tensile force of glass fiber mesh”, Textile Science and Engineering, v. 55, n. 6, pp. 373–380, 2018.]. In both developed and developing nations, many forms of public-private partnerships (PPPs) are used to create infrastructure. On the one hand, this strategy has resulted in the productive development of projects, but on the other hand, PPPs have faced several problems across the nation. One difficulty is the sluggish speed at which PPPs are implemented, this way of built in infrastructure results in tiny percentage [12[12] SHANNAG, M.J., ZIYYAD, T.B., “Flexural response of ferrocement with fibrous cementitious matrices”, Construction & Building Materials, v. 21, n. 6, pp. 1198–1205, 2007. doi: http://doi.org/10.1016/j.conbuildmat.2006.06.021.
https://doi.org/10.1016/j.conbuildmat.20...
]. PPP-projects fail or being abandoned, putting both the proponents and the funding institutions in a financial bind. As a result, an efficient procurement strategy is essential for future PPP projects to enhance standards. A lot of factors impact whether an infrastructure project succeeds or fails in terms of price, time, and quality. The KSF (Key Success Factor ) for these goals will be established in order to make the most optimal usage of the limited resources available [13[13] FRANCIOSO, V., MORO, C., CASTILLO, A., et al., “Effect of elevated temperature on flexural behavior and fibers-matrix bonding of recycled PP fiber-reinforced cementitious composite”, Construction & Building Materials, v. 269, pp. 121243, 2021. doi: http://doi.org/10.1016/j.conbuildmat.2020.121243., 14[14] DASKIRAN, E.G., DASKIRAN, M.M., GENCOGLU, M., “Experimental investigation on impact strength of AR glass, Basalt and PVA textile reinforced cementitious composites”, European Journal of Environmental and Civil Engineering, v. 26, n. 6, pp. 2037–2056, 2022. doi: http://doi.org/10.1080/19648189.2020.1749940.
https://doi.org/10.1080/19648189.2020.17...
]. The public sector as a whole has a rich history of awarding a contract to the lowest bidder. A low-bid approach, on the other hand, encourages contractors to use cost-cutting tactics rather than quality-improvement measures, making it likely that the contract will be awarded to the best-performing contractors who can provide the best goods [15[15] TSESARSKY, M., PELED, A., KATZ, A., et al., “Strengthening concrete elements by confinement within textile reinforced concrete (TRC) shells – Static and impact properties”, Construction & Building Materials, v. 44, pp. 514–523, 2013. doi: http://doi.org/10.1016/j.conbuildmat.2013.03.031.
https://doi.org/10.1016/j.conbuildmat.20...
, 16[16] THANGARAJ, R.P., SHANMUGAM, B., “A review paper on mechanical properties of flexural and impact test on textile reinforced engineered cementitious composites”, Materials Today: Proceedings, v. 50, pp. 2160–2169, 2022. doi: http://doi.org/10.1016/j.matpr.2021.09.443.
https://doi.org/10.1016/j.matpr.2021.09....
]. As a result, public shareholders are increasingly seeking methods to include non-price aspects into the procurement process, both qualitative and quantitative, to motivate construction companies to not only enhance their productivity during work but also to add value to the finished items [17[17] NASSANI, D.E., “Experimental and analytical study of the mechanical and flexural behavior of hybrid fiber concretes”, Structures, v. 28, pp. 1746–1755, 2020. doi: http://doi.org/10.1016/j.istruc.2020.10.014.
https://doi.org/10.1016/j.istruc.2020.10...
, 18[18] CHANDRA, V.B., CHARI, K.B., RAO, V.R., “The comprehensive analytical investigation on blended cement concrete beams with glass fibers under flexural loading”, Materials Today: Proceedings, v. 33, pp. 587–592, 2020. doi: http://doi.org/10.1016/j.matpr.2020.05.498.
https://doi.org/10.1016/j.matpr.2020.05....
]. The goal of this article is to determine Key success factors for BOT projects to contribute towards the development of methodologies and tools that will assist proprietors and/or builders in completing construction projects on time, on budget, and to a predetermined quality standard [19[19] SANJEEV, J., NITESH, K.S., “Study on the effect of steel and glass fibers on fresh and hardened properties of vibrated concrete and self-compacting concrete”, Materials Today: Proceedings, v. 27, pp. 1559–1568, 2020. doi: http://doi.org/10.1016/j.matpr.2020.03.208.
https://doi.org/10.1016/j.matpr.2020.03....
, 20[20] SHANOUR, A.S., SAID, M., ARAFA, A.I., et al., “Flexural performance of concrete beams containing engineered cementitious composites”, Construction & Building Materials, v. 180, pp. 23–34, 2018. doi: http://doi.org/10.1016/j.conbuildmat.2018.05.238.
https://doi.org/10.1016/j.conbuildmat.20...
]. It all starts with a thorough review of the literature in order to discover and describe widely held construction management knowledge. This study aims to shift away from traditional risk mitigation, which concentrates on risks, toward strategic decision-making, which focuses on achieving win-win outcomes [21[21] JOHN, S.K., NADIR, Y., GIRIJA, K., et al., “Tensile behaviour of glass fibre textile reinforced mortar with fine aggregate partially replaced by fly ash”, Materials Today: Proceedings, v. 27, pp. 144–149, 2020. doi: http://doi.org/10.1016/j.matpr.2019.09.135.
https://doi.org/10.1016/j.matpr.2019.09....
, 22[22] ÖZKAN, Ş., DEMIR, F., “The hybrid effects of PVA fiber and basalt fiber on mechanical performance of cost effective hybrid cementitious composites”, Construction & Building Materials, v. 263, pp. 120564, 2020. doi: http://doi.org/10.1016/j.conbuildmat.2020.120564.]. The study includes:

  1. Perform a field-survey using a questionnaire and one to one discussions to discover the principal reasons for construction delay for both conventional and BOT operations, as well as the perspectives of three important stakeholders: the client, consultant, and contractor.

  2. Using SPSS (Statistical Package for Social Sciences) to identify the critical Key success criteria for BOT initiatives based on industry experts’ expertise and opinions (SPSS).

  3. To identify and debate a variety of issues, such as strategic planning, that government should tackle in order for the BOT process to work well.

  4. Using Multi-attribute decision theory, develop a “decision support system” for making appropriate choices for BOT promoters in order to provide excellent value to the public procurer.

SPSS is often preferred by researchers because of its user-friendly interface and extensive capabilities. RII, is a statistical technique used to assess the relative importance of different variables in explaining a particular outcome. Large number of unknown variables can be analyzed in a fastest and more reliable way, in this case, SPSS nor RII is inherently more reliable than other approaches.

2. METHODOLOGY

Construction project management covers various critical aspects, such as managing risks in large infrastructure projects, dealing with delays, identifying key success drivers, learning from global BOT practices, selecting contractors, and employing best value selection models [23[23] KANG, S.T., LEE, B.Y., KIM, J.-K., et al., “The effect of fibre distribution characteristics on the flexural strength of steel fibre-reinforced ultra high strength concrete”, Construction & Building Materials, v. 25, n. 5, pp. 2450–2457, 2011. doi: http://doi.org/10.1016/j.conbuildmat.2010.11.057.
https://doi.org/10.1016/j.conbuildmat.20...
]. These areas are extensively investigated through surveys of peer-reviewed literature. However, the summary provided only includes a small portion of the most significant sources [24[24] CHOI, J.-I., LEE, B.Y., “Bonding properties of basalt fiber and strength reduction according to fiber orientation”, Materials (Basel), v. 8, n. 10, pp. 6719–6727, 2015. doi: http://doi.org/10.3390/ma8105335. PubMed PMID: 28793595.
https://doi.org/10.3390/ma8105335...
]. Additionally, the study includes a postal questionnaire survey to assess the factors that cause delays in BOT projects. Furthermore, interviews are conducted with different construction project stakeholders to gain a better understanding of the fundamental causes of these delays [8[8] GOH, C.S., ABDUL-RAHMAN, H., “The identification and management of major risks in the Malaysian construction industry”, Journal of Construction in Developing Countries, v. 18, n. 1, pp. 19–32, 2013.]. Out of 520 individuals contacted for a survey on success factors for BOT projects in India, 380 responded (73% response rate). The survey included questionnaires sent via mail to 220 contractors (42%), 170 consultants (33%), and 180 clients (25%) as shown in Figure 1. This statistically significant data provides valuable insights into BOT project construction in India. The study also indicates the obstacles the government must overcome in order for the BOT network to operate properly [25[25] SANTOS, I.G., ESPINDOLA, R.P., ARAGÃO, F.T.S., et al. “ A statistical methodology for reliable evaluation of calibrated dynamics modulus regression models”, Matéria (Rio de Janeiro), v. 28, n. 4, pp. e20230188, 2023. doi: https://doi.org/10.1590/1517-7076-RMAT-2023-0188.
https://doi.org/10.1590/1517-7076-RMAT-2...
]. This research investigates a novel approach to promoter selection for India’s BOT projects within Public-Private Partnerships (PPP), prioritizing public sector value. It proposes a two-fold solution: a comprehensive framework evaluating promoters based on critical project success factors like technical expertise, financial strength, and managerial capabilities. This framework will be complemented by a decision-support system built using the .NET framework. This system will leverage SPSS software and multi-attribute decision-making analysis to improve efficiency in promoter selection, particularly when faced with incomplete information. Ultimately, this approach aims to enhance infrastructure project outcomes.

Figure 1
Respondent types.

3. EXPERIMENTAL ANALYSIS

3.1. Analysis of time delay

To assess the extent of time overruns in building projects and identify the contributing factors, researchers conduct a postal survey using a three-part questionnaire. The questionnaire is divided into three parts. The first part focuses on six key factors that influence how important time is in both traditional and BOT (Build-Operate-Transfer) projects. It also explores the extent to which different organizations experience schedule delays.The second and third sections delve into the reasons behind schedule overruns in both conventional and BOT projects.Totally 50 factors are identified through the literature study. The study examines: contractor, consultant and client-related elements. This classification aims to determine the extent of the issue, allocate responsibility, and identify potential actions to mitigate time delays. Variables affecting owners, contractors, and consultants are directly attributed to these professionals, while the construction manager addresses project-related and external-related concerns based on the specific scenario [26[26] BARRA, B.S., MOMM, L., PEREZ, Y.A.G., “A new dynamic apparatus for asphalt mix fatigue and stiffness modulus: development, validation and numerical simulations”, Matéria (Rio de Janeiro), v. 27, n. 1, pp. e13130, 2022. doi: https://doi.org/10.1590/S1517-707620220001.1330.
https://doi.org/10.1590/S1517-7076202200...
]. The Initial part of the poll plots the perception of respondent’s abouts their perception of time overrun. For both traditional and BOT projects, respondents will be asked to determine the relative importance of each attribute on the project’s schedule overrun on a scale of 1 to 5, with 5 being the most significant and 1 being the least significant (where 5 = Strongly Agree, 4 = Agree, 3 = Neutral, 2 = Disagree, and 1 = Strongly Disagree).

3.1.1. Analysis of the survey

According to the Preliminary report, time overruns occur in more than 70 percent of typical construction projects, with the owner, contractor, and consultant each contributing 50, 40, and 10% of time overruns, respectively. Regardless of project size, time overruns are unaffected. A survey revealed a surprising prioritization for BOT and infrastructure projects. As shown in Figure 2, completing construction within the planned timeframe is considered the most critical objective, followed by quality. Interestingly, cost comes in last. This prioritization can likely be attributed to the unique cash flow of BOT projects. Since revenue generation typically begins only after the project is operational, timely completion becomes paramount.

Figure 2
BOT projects (Objective Importance).

The second most critical element is identified as the quality which indicates the need for maintining the facility during the period of operation. On the other hand, cost control should be justified, although it is not as essential in BOT projects as time and quality. Timing delays are infrequently encountered during the construction of BOT projects.. The majority of the delays are due to an insufficient lawful and governing framework. The data is evaluated using the Relative Important Index (RII). To assess the relative importance of each element in creating project time overruns. The following equation is used to calculate the relative importance index (RII):

RII=W/(A×N)(1)

Where W denotes the respondents’ weights for each element, which vary from 1 to 5. A represents the most significant weight, and N = total number of respondents. The analysis is carried out separately for each of the three types of respondents. The overall rating as well as the ranking by category are determined. The top 10 factors influencing traditional project time overruns are analyzed in Table 1.

Table 1
Factors influencing traditional project time overrun.

The study has therefore listed ten major concerns for delay in BOT Projects across India. Promoter aims to maximize the project’s profitability by expediting the building construction process. Jy-Bin Yang discovered delay factors at various phases of BOT projects through two questionnaire surveys based on his perception of BOT participant. Based on the study’s findings, the major factors contributing to delays in BOT projects include the negotiation stage of concession contracts leading to the awarding of concessions to contractors, political instability, concerns related to debt, and government-finished goods. Table 2 shows the Factors influencing BOT project time overruns.

Table 2
Factors influencing BOT project time overruns.

3.2. The questionnaire survey’s validity and reliability

To ensure the questionnaire’s quality, the researchers performed a validity analysis (VA) and reliability analysis (RA). VA aimed to confirm whether the questionnaire effectively measured the intended variables. The rankings of delay variables were determined based on the responses from all participants. One interesting aspect of the study was observing how different individuals ranked these delay characteristics [8[8] GOH, C.S., ABDUL-RAHMAN, H., “The identification and management of major risks in the Malaysian construction industry”, Journal of Construction in Developing Countries, v. 18, n. 1, pp. 19–32, 2013.]. For the rank agreement analysis, the researchers employed a quantitative technique introduced by Goh, which utilized the “rank agreement factor” (RAF). Calculation of RAF is the absolute average difference in factor rankings between two groups. This approach helped to assess the level of agreement or disagreement in how delay factors were ranked by different sets of participants. Such analyses are crucial in ensuring the robustness and credibility of the research findings.

If there is two groups, the rank of the ith item be Ri1 (group 1) and Ri2 (group 2), let N be the number of items, and j = N−i + 1.

The RAF=i=1N|RR|N(2)
The RAF is defined as, RAF = The maximum rank agreement factor (RAFmax) is defined as the percentage agreement (PA) is defined as PA = 100 – PD The lesser the agreement between the two groups, the higher the RAF value. A RAF of zero indicates complete agreement. It can be shown that all three sets of respondents, contractor-consultant, consultant-owner, and contractor-owner, have a high level of agreement in rating of delay factors, showing that the study is legitimate and trustworthy.

3.2.1. Analysis of factors

Factor analysis is a useful technique for identifying crucial elements among various potential causes. In this study, the researchers employed the Kaiser-Meyer-Olkin test and Bartlett’s test of specificity for factor analysis. The Kaiser-Meyer-Olkin (KMO) test measures the ratio of quadratic correlation between variables to quadratic partial correlation between variables, ranging from 0 to 1. Higher KMO coefficients close to one indicate more reliable and compact relationships among variables. In this research, factors with KMO values greater than 0.50 were considered, resulting in 29 out of 45 factors being examined, while the other 16 factors were excluded due to their lack of meaningful associations with other variables. The correlation matrix, confirmed by Bartlett’s test with a significance value of 0.001, indicated high interconnections among variables. Principal component analysis was then employed to reduce the highly connected factors into a smaller number of essential elements. With a minimum starting eigenvalue of 1.0, five main components were extracted, explaining 71.30 percent of the total variance. To assess the agreement among respondents on the element rankings, Spearman’s rank correlation was used. Higher correlation values imply greater agreement between respondents. The results showed substantial connections between the three pairs of respondents (Client, Consultant, and Contractor) in rating the factors, with significant loadings of 82 percent, 78.1 percent, and 73.5 percent, respectively (Table 3).

Table 3
Analysis of factors.

3.2.2. Regression analysis

The study of the connection among variables is known as regression analysis. The control variables are organized into five categories, as indicated in Table 4, and the dependent variables are cost, quality, and time, all of which are related to project completion. To assess the quantifiable impacts of the components, regression analysis models are created, and the performance is tested in equation 1 [27[27] JABAR, A.B., PRADEEP, T., “ANN-PSO modelling for predicting bucking of self-compacting concrete column containing RHA properties”, Matéria (Rio de Janeiro), v. 28, n. 2, pp. e20230102, 2023. doi: https://doi.org/10.1590/1517-7076-RMAT-2023-0102.
https://doi.org/10.1590/1517-7076-RMAT-2...
].

Table 4
Regression analysis.

Yi=β0+β1α1i+β2α2i++βjαjiεi(3)
Where Y represents the value of the dependent variables, β0 represents the constant, β1 to βj represents the regression coefficient, α1 to αn represents the values of the independent variables, and εi represents random error. The Spearman correlational analysis (SCA) was used to see if there was a link between the elements that influence formwork system selection. The SCA is employed to identify the independent variable that exhibits a significant correlation with the three criteria of cost, quality, and time. In the regression analysis, the independent factors are individually examined against the outcome variables of quality, cost, and time [28[28] ZHOU, X., XIE, J., ZHANG, M., “Numerical analysis of combined optimization of turbine runner flow pattern and shafting system”, Matéria (Rio de Janeiro), v. 27, n. 4, pp. e20220172, 2022. doi: https://doi.org/10.1590/1517-7076-RMAT-2022-0172.
https://doi.org/10.1590/1517-7076-RMAT-2...
]. The model is chosen based on correlation strength, which is a measure of the model’s quality of fit. When additional independent variables are introduced, the value of R2 changes, and the model’s modified R2 is calculated.

3.3. Identification of key success factors (KSF)

Previous studies on Build-Operate-Transfer (BOT) projects often overlooked non-physical factors when identifying key success elements (KSFs) is shown in Figure 3. This research addresses this gap by proposing a systematic method to identify and analyze KSFs, encompassing both tangible and intangible aspects.The method leverages expert opinions through a well-established approach to ensure consistency [29[29] SOUZA, L.A.F., VANALLI, L., VANDERLEI, R.D. et al., “Nonlinear numerical model of plane frames considering semi-rigid connection and different beam theories”, Matéria (Rio de Janeiro), v. 26, n. 3, pp. e13037, 2021. doi: https://doi.org/10.1590/S1517-707620210003.13037.
https://doi.org/10.1590/S1517-7076202100...
]. This comprehensive model empowers better decision-making for BOT initiatives by considering all relevant factors, not just physical ones.

Figure 3
Success of the project using a hierarchy model.

In this study, six key success factors (KSFs) are identified, each comprising various sub-factors (SFs) [30[30] SANTOS, R.A., MEIRA, G.R., BEZERRA, W.V.D.C., et al., “Use of numerical method for optimization of granulometric curves in eco-efficient concrete”, Matéria (Rio de Janeiro), v. 26, n. 4, pp. e13115, 2021. doi: https://doi.org/10.1590/S1517-707620210004.1315.
https://doi.org/10.1590/S1517-7076202100...
]. Validating the SPSS methodology, a questionanaire survey is conducted using the Relative Importance Index (RII) approach, and the obtained results are consistent. The extracted ten factors in the Table 10 by SPSS approach are compared to those identified by the RII method and also to earlier research conducted worldwide (Table 5).

Table 5
Success factors taken for SPSS analysis.

3.3.1. KSF’S agreement analysis

The ranking of KSF’s for BOT projects is determined using two independent approaches, the RII method and the SPSS methodology, based on responses to two surveys created specifically for the purpose. Given the variance in KSF rankings discovered, determining the amount of understanding between the two methodologies’ rankings of these factors is crucial. The percentage of agreement (PA) for recognizing KSFs between the two techniques is 84.5 percent. As a consequence, the ranking between the RII and SPSS techniques has a high level of agreement (>85%), showing that the survey questionnaire is consistent in Table 6.

Table 6
Top factors.

3.4. Discussion on top factors

The cornerstone of a successful project is a well-crafted concession agreement. This contract outlines a public entity leasing an asset to a private company for extended service provision. The private party also agrees to fund additional fixed projects during the lease. This structure aims to optimize public spending while delivering efficient and cost-effective services to users. A strong concession agreement acts as a legal and policy roadmap, attracting private investment and promoting efficiency. A short construction timeframe is crucial, not only for early user access but also for faster revenue generation, ultimately boosting project profitability. While a brief construction period is a vital element within the broader technical solution, it wasn’t explicitly mentioned in Zhang’s research. However, his focus on adequate project profitability to attract investors aligns with this concept. For Build-Operate-Transfer (BOT) projects, financial success is paramount as project revenue solely funds debt repayment and promoter dividends. Long-term user demand and positive cash flow are essential for a project to be considered financially viable by lenders. The financing strategy significantly impacts risk mitigation in BOT projects, as project income is the sole source of repayment. Project sponsors often utilize loan agreements to optimize long-term debt and minimize refinancing risks. Strong leadership with expertise in foreign BOT project management is crucial. The concessionaire needs a capable leader with a proven track record and good relationships with government officials. A well-defined concession agreement should provide flexibility for the concessionaire to innovate and implement cost-effective designs without compromising service quality. This flexibility can lead to cost savings through innovative designs driven by output-based requirements.

3.5. Government aid and financial schemes

Large infrastructure projects, especially those financed through Build-Operate-Transfer (BOT) agreements, expose sponsors to a multitude of challenges. These risks, if not carefully mitigated, can lead to project failure. The inherent complexities of PPP projects, encompassing aspects like documentation, funding, taxes, technical specifications, sub-contracts, and other large-scale project intricacies, contribute significantly to the overall risk profile. Additionally, the nature of these risks evolves throughout the project lifecycle. For instance, risks encountered during the construction phase differ from those faced during the operational phase. Broadly, these risks can be classified into two categories: elemental risks and global risks. Elemental risks, encompassing aspects like physical risks, design flaws, construction issues, operation and maintenance challenges, technological disruptions, financial constraints, and revenue generation shortfalls, are generally considered more manageable than global risks [5[5] ABD KARIM, N.A., RAHMAN, I.A., MEMMON, A.H., et al., “Significant risk factors in construction projects: Contractor’s perception”, In: 2012 IEEE Colloquium on Humanities, Science and Engineering (CHUSER), pp. 347–350, Kota Kinabalu, Malaysia, 2012. doi: http://doi.org/10.1109/CHUSER.2012.6504337.
https://doi.org/10.1109/CHUSER.2012.6504...
]. Global risks, on the other hand, encompass political, legal, commercial, and environmental factors that can significantly impact project outcomes. Literature suggests that effectively managing elemental risks is essential for BOT projects, given the intricate relationships between the involved parties. While many of these risks are common across various project financing endeavors, their severity varies depending on the specific project. Fortunately, established methodologies can be applied to assess these risks. A critical challenge lies in ensuring that the project’s revenue streams are sufficient to cover operational expenses, service debt obligations, and provide returns on invested capital.

3.5.1. Menace analysis

A BOT procurement typically involves three key parties: 1. The public entity initiating the project, often a government agency. 2. The private company or consortium financing, building, and operating the project for a set period. 3. The financial institutions lending money for the project’s development. Typical relationship between principal participants in BOT type procurement is shown in Figure 4.

Figure 4
Typical relationship between principal participants in BOT type procurement.

From the perspective of the project’s major stakeholders, the flow diagram of the project risk graph of the analytical approach is examined is shown in Figure 5. In the government’s view, spending should be optimized. They aim to get the most value by involving private companies. This could involve private sector expertise in planning, building, and running the project, all under government oversight. However, transferring risks like design flaws, delays, and cost increases to private companies can be an illusion. Public-Private Partnerships (PPPs) often rely on a specially created entity to manage the project. This entity depends on future revenue to cover costs and debt, ensuring a return for the private investor. However, long-term income is crucial for PPP success. Without it, the project might fail. Since individual ownership in PPPs is rare, lenders bear the risks. They rely on project cash flow for repayment, with no recourse to the original companies. In infrastructure projects, especially transportation, the assets themselves often don’t provide enough security for lenders. Cash flow becomes their primary source of protection. Ideally, lenders would want not just sufficient cash flow, but also the ability to transfer the concession (operating rights) to another company if the current operator fails. Researchers have proposed a decision model based on case studies, which can help project sponsors choose a financial strategy based on the expected risks over the project’s lifespan. This model considers the predicted level of financial, political, and market risks, as detailed in Table 7.

Figure 5
Analytical approach flow chart.
Table 7
Possible financial menace strategy.

3.6. Decision model for granting the contract

Public sector contracts, including those involving Build-Operate-Transfer (BOT) agreements, often rely on open competitive bidding to choose a contractor or concessionaire. This method prioritizes the lowest price, which can encourage competition but doesn’t guarantee the selection of the best contractor for the job quality. To reduce effects and improve long-term performance and value of construction, a procurement strategy that considers pricing and other critical elements in the assessment process is required. Based on the aforementioned premise the optimal value model is produced. The decision model for granting the contract is examined is shown in Figure 6.

Figure 6
Decision model for granting the contract.

Awarding concessions in India and elsewhere often follows a transparent bidding process. All project details, such as the duration, toll fees, price adjustments, and technical requirements, are clearly outlined upfront. Shortlisted bidders then simply state the amount of financial support they require. The project is awarded to the bidder seeking the least subsidy. In rare cases, a bidder might propose revenue sharing with the awarding body instead of a grant. This structure ensures unbiased, fair, and thorough evaluation of bids. However, to counter potential cost-cutting measures associated with low-bid systems, project owners often rely heavily on prequalification. This prequalification stage becomes critical in selecting qualified bidders and guaranteeing the success of construction endeavors. In many cases, initial responses to invitations for significant infrastructure projects do not necessitate extensive presentations.

3.7. Promoter selection using .net framework

To identify potential bids for BOT projects in India, a pre-qualification procedure is used. The RFQ document describes the assessment criteria as well as the bidding process timetable. Many government agencies, including national departments like the National Highways Authority of India (NHAI) and the Ministry of Surface Transport, as well as state-level bodies like Housing Boards and Road Development Authorities, are utilizing public-private partnerships (PPPs) for infrastructure development. However, selecting suitable partners for these complex projects requires a more holistic approach than traditional methods. While technical expertise and financial strength (net worth, cash flow, and earnings) are crucial, factors like managerial skills, entrepreneurial spirit, and leadership are often undervalued. Unfortunately, the contractor selection process is often hampered by limited or incomplete information about both the project itself and the potential partners. This necessitates decision-making based on imperfect data, requiring a more nuanced evaluation. The handy technique is analyzed for dealing with imprecise and ambiguous information when making decisions. The paper proposes a framework for solving construction contractor prequalification based on SPSS and multi-attribute decision-making analysis, which involves constructing a decision support system that can also handle language factors. The difficulty of evaluating candidates is reduced to a problem of multi-attribute decision-making, in which the owner may have competing objectives of varying priority (weights). The problem is organized in the following order by the methodology. • Step 1: Establish fundamental requirements • Step 2: Break down core criteria into smaller groupings, eventually becoming a single criterion. • Step 3: Sort the applicants into groups.

In the fourth step, we conduct a .NET Framework analysis. This analysis examines how adjustments to the criteria weights impact the ranking of potential options (alternatives). A pairwise comparison matrix is used to assess the relative importance of various promoters across multiple key criteria at level 5. This helps determine the decision-makers’ preferences for these promoters. The final score for each promoter is calculated by considering the relative importance matrix of applicant promoters against various features, along with their corresponding weights at levels 4, 3, and 2.

.Net Framework Analysis is a popular MySQL management tool, particularly for web hosting provider. PHP is an HTML-enabled server-side programming language. It’s used to handle dynamic content, databases, track sessions, and even develop full e-commerce sites. To interpret PHP script instructions, a processor must be installed in order to generate generic HTML result that can be delivered to a web browser. This will be accomplished by asking a few extra questions of the application’s end user. Figure 7 shows the hierarchy of a four-package set of criteria for evaluating applications. This system will determine which sort of Promoter is appropriate for the build based on the user’s input. Software Requirement - Front End: local host, Back End: Php my admin, OS: Windows XP, 7, 8, Hard Disk: 20 GB (Min), RAM: 512 MB (Min)

Figure 7
Evaluation package list.

4. CONCLUSION

The goal of this study is to recommend and implement specific methods that will be beneficial to governments, financial institutions, owners, and/or contractors in successfully completing massive infrastructure projects on time, on budget, and to a high standard. To identify the elements causing time overruns, a postal survey is utilized to study the relative relevance and significant factors. Findings are compared to Past research works. A hierarchical success model is built for identifying essential success variables. The SPSS and RII methods are used to analyze the data obtained from experts individually. The findings are compared to those of earlier research. An agreement analysis is performed to validate the results. By altering the entire construction length, the influence of a project’s short construction term on its profitability is investigated in this study effort. It has been noticed that even if more money is spent to reduce construction time, the project’s total profitability improves dramatically. From the perspectives of many important parties, the various forms of risk experienced in BOT projects are examined. Political, financial, and market risk are considered to be the most important project risks. This report explores how BOT (Build-Operate-Transfer) project promoters can select the most cost-effective financial approach. While a simple low-bid strategy might seem appealing, it can overlook the bigger picture. To ensure the project’s long-term success, a best-value contracting approach is recommended. This method considers not just price, but also other critical factors during the evaluation and selection process. A unique best-value modelling concept is introduced, allowing for a customized approach for each project. This model identifies and analyzes the key criteria that influence choosing the best concessionaire. In India and many other countries, selecting a concessionaire follows a transparent competitive bidding process. All project details, including the concession period, toll rates, pricing adjustments, and technical requirements, are clearly communicated beforehand. Shortlisted bidders then only need to submit their desired grant amount. The contract should go to the bidder that requests the smallest grant. In extreme circumstances, a bidder may offer to split project income with the authority rather than requesting a grant. The paper describes the prequalification method used in India and other developed and developing nations to choose suitable bidders for BOT projects. In most cases, owners carefully assess bidders using established criteria. Selecting qualified sponsors for infrastructure projects is a complex process that considers multiple factors and requires careful evaluation due to the ever-changing environment. According to the unique project parameters, an SPSS-based framework for rating diverse applications is presented. The framework entails the identification of basic criteria and the weighting of those factors, as well as methodical aggregation and, eventually, the ranking of candidates for prequalification. The model is implemented to analyze the variations caused by changes in the values of input parameters, a simple approach is created to provide a regression analysis of the problem. For the examination of numerous risk factors and uncertainties associated with BOT projects, more research is needed. At the most basic level, regression analysis may be used to assess all of the criteria.

5. ACKNOWLEDGMENTS

The authors wish to acknowledge Department of civil engineering, KPR Institute of Engineering and Technology, Coimbatore, Tamil Nadu for the facility and support extended for the research work.

6. BIBLIOGRAPHY

  • [1]
    KARTAM, N.A., KARTAM, S.A., “Risk and its management in the Kuwaiti construction industry: a contractors’ perspective”, International Journal of Project Management, v. 19, n. 6, pp. 325–335, 2001. doi: http://doi.org/10.1016/S0263-7863(00)00014-4.
    » https://doi.org/10.1016/S0263-7863(00)00014-4
  • [2]
    ABEDNEGO, M.P., OGUNLANA, S.O., “Good project governance for proper risk allocation in public–private partnerships in Indonesia”, International Journal of Project Management, v. 24, n. 7, pp. 622–634, 2006. doi: http://doi.org/10.1016/j.ijproman.2006.07.010.
    » https://doi.org/10.1016/j.ijproman.2006.07.010
  • [3]
    ADNAN, H., RAHMAT, M.N., FATANAH, N., et al, “Risk management assessment for partnering projects in the Malaysian Construction Industry”, Journal of Politics and Law, v. 1, n. 1, pp. 76–81, 2008. doi: http://doi.org/10.5539/jpl.v1n1p76.
    » https://doi.org/10.5539/jpl.v1n1p76
  • [4]
    ALGAHTANY, M., ALHAMMADI, Y., KASHIWAGI, D., “Introducing a new risk management model to the Saudi Arabian construction industry”, Procedia Engineering, v. 145, pp. 940–947, 2016. doi: http://doi.org/10.1016/j.proeng.2016.04.122.
    » https://doi.org/10.1016/j.proeng.2016.04.122
  • [5]
    ABD KARIM, N.A., RAHMAN, I.A., MEMMON, A.H., et al, “Significant risk factors in construction projects: Contractor’s perception”, In: 2012 IEEE Colloquium on Humanities, Science and Engineering (CHUSER), pp. 347–350, Kota Kinabalu, Malaysia, 2012. doi: http://doi.org/10.1109/CHUSER.2012.6504337.
    » https://doi.org/10.1109/CHUSER.2012.6504337
  • [6]
    KANDASAMY, Y., THANGAVEL, B., SUKUMAR, K.K., et al, “Strength properties of engineered cementitious composites containing pond ash and steel fiber”, Matéria (Rio de Janeiro), v. 29, n. 1, pp. e20230277, 2024. doi: http://doi.org/10.1590/1517-7076-rmat-2023-0277.
    » https://doi.org/10.1590/1517-7076-rmat-2023-0277
  • [7]
    ASSAF, S.A., AL-HEJJI, S., “Causes of delay in large construction projects”, International Journal of Project Management, v. 24, n. 4, pp. 349–357, 2006. doi: http://doi.org/10.1016/j.ijproman.2005.11.010.
    » https://doi.org/10.1016/j.ijproman.2005.11.010
  • [8]
    GOH, C.S., ABDUL-RAHMAN, H., “The identification and management of major risks in the Malaysian construction industry”, Journal of Construction in Developing Countries, v. 18, n. 1, pp. 19–32, 2013.
  • [9]
    ZHANG, T., WANG, B., LU, X., et al, “Flexural properties of textile-reinforced concrete with nonorthogonal grids”, Polymers, v. 14, n. 23, pp. 5185, 2022. doi: http://doi.org/10.3390/polym14235185. PMid:36501580.
    » https://doi.org/10.3390/polym14235185
  • [10]
    YOU, J., PARK, J., PARK, S.-K., et al, “Experimental study on the flexural behavior of steel-textile-reinforced concrete: various textile reinforcement details”, Applied Sciences (Basel, Switzerland), v. 10, n. 4, pp. 1425, 2020. doi: http://doi.org/10.3390/app10041425.
    » https://doi.org/10.3390/app10041425
  • [11]
    KIM, S.H., LEE, S.H., “Study on flexural strength of textile-reinforced mortar panel with tensile force of glass fiber mesh”, Textile Science and Engineering, v. 55, n. 6, pp. 373–380, 2018.
  • [12]
    SHANNAG, M.J., ZIYYAD, T.B., “Flexural response of ferrocement with fibrous cementitious matrices”, Construction & Building Materials, v. 21, n. 6, pp. 1198–1205, 2007. doi: http://doi.org/10.1016/j.conbuildmat.2006.06.021.
    » https://doi.org/10.1016/j.conbuildmat.2006.06.021
  • [13]
    FRANCIOSO, V., MORO, C., CASTILLO, A., et al, “Effect of elevated temperature on flexural behavior and fibers-matrix bonding of recycled PP fiber-reinforced cementitious composite”, Construction & Building Materials, v. 269, pp. 121243, 2021. doi: http://doi.org/10.1016/j.conbuildmat.2020.121243.
  • [14]
    DASKIRAN, E.G., DASKIRAN, M.M., GENCOGLU, M., “Experimental investigation on impact strength of AR glass, Basalt and PVA textile reinforced cementitious composites”, European Journal of Environmental and Civil Engineering, v. 26, n. 6, pp. 2037–2056, 2022. doi: http://doi.org/10.1080/19648189.2020.1749940.
    » https://doi.org/10.1080/19648189.2020.1749940
  • [15]
    TSESARSKY, M., PELED, A., KATZ, A., et al, “Strengthening concrete elements by confinement within textile reinforced concrete (TRC) shells – Static and impact properties”, Construction & Building Materials, v. 44, pp. 514–523, 2013. doi: http://doi.org/10.1016/j.conbuildmat.2013.03.031.
    » https://doi.org/10.1016/j.conbuildmat.2013.03.031
  • [16]
    THANGARAJ, R.P., SHANMUGAM, B., “A review paper on mechanical properties of flexural and impact test on textile reinforced engineered cementitious composites”, Materials Today: Proceedings, v. 50, pp. 2160–2169, 2022. doi: http://doi.org/10.1016/j.matpr.2021.09.443.
    » https://doi.org/10.1016/j.matpr.2021.09.443
  • [17]
    NASSANI, D.E., “Experimental and analytical study of the mechanical and flexural behavior of hybrid fiber concretes”, Structures, v. 28, pp. 1746–1755, 2020. doi: http://doi.org/10.1016/j.istruc.2020.10.014.
    » https://doi.org/10.1016/j.istruc.2020.10.014
  • [18]
    CHANDRA, V.B., CHARI, K.B., RAO, V.R., “The comprehensive analytical investigation on blended cement concrete beams with glass fibers under flexural loading”, Materials Today: Proceedings, v. 33, pp. 587–592, 2020. doi: http://doi.org/10.1016/j.matpr.2020.05.498.
    » https://doi.org/10.1016/j.matpr.2020.05.498
  • [19]
    SANJEEV, J., NITESH, K.S., “Study on the effect of steel and glass fibers on fresh and hardened properties of vibrated concrete and self-compacting concrete”, Materials Today: Proceedings, v. 27, pp. 1559–1568, 2020. doi: http://doi.org/10.1016/j.matpr.2020.03.208.
    » https://doi.org/10.1016/j.matpr.2020.03.208
  • [20]
    SHANOUR, A.S., SAID, M., ARAFA, A.I., et al, “Flexural performance of concrete beams containing engineered cementitious composites”, Construction & Building Materials, v. 180, pp. 23–34, 2018. doi: http://doi.org/10.1016/j.conbuildmat.2018.05.238.
    » https://doi.org/10.1016/j.conbuildmat.2018.05.238
  • [21]
    JOHN, S.K., NADIR, Y., GIRIJA, K., et al, “Tensile behaviour of glass fibre textile reinforced mortar with fine aggregate partially replaced by fly ash”, Materials Today: Proceedings, v. 27, pp. 144–149, 2020. doi: http://doi.org/10.1016/j.matpr.2019.09.135.
    » https://doi.org/10.1016/j.matpr.2019.09.135
  • [22]
    ÖZKAN, Ş., DEMIR, F., “The hybrid effects of PVA fiber and basalt fiber on mechanical performance of cost effective hybrid cementitious composites”, Construction & Building Materials, v. 263, pp. 120564, 2020. doi: http://doi.org/10.1016/j.conbuildmat.2020.120564.
  • [23]
    KANG, S.T., LEE, B.Y., KIM, J.-K., et al, “The effect of fibre distribution characteristics on the flexural strength of steel fibre-reinforced ultra high strength concrete”, Construction & Building Materials, v. 25, n. 5, pp. 2450–2457, 2011. doi: http://doi.org/10.1016/j.conbuildmat.2010.11.057.
    » https://doi.org/10.1016/j.conbuildmat.2010.11.057
  • [24]
    CHOI, J.-I., LEE, B.Y., “Bonding properties of basalt fiber and strength reduction according to fiber orientation”, Materials (Basel), v. 8, n. 10, pp. 6719–6727, 2015. doi: http://doi.org/10.3390/ma8105335. PubMed PMID: 28793595.
    » https://doi.org/10.3390/ma8105335
  • [25]
    SANTOS, I.G., ESPINDOLA, R.P., ARAGÃO, F.T.S., et al “ A statistical methodology for reliable evaluation of calibrated dynamics modulus regression models”, Matéria (Rio de Janeiro), v. 28, n. 4, pp. e20230188, 2023. doi: https://doi.org/10.1590/1517-7076-RMAT-2023-0188.
    » https://doi.org/10.1590/1517-7076-RMAT-2023-0188
  • [26]
    BARRA, B.S., MOMM, L., PEREZ, Y.A.G., “A new dynamic apparatus for asphalt mix fatigue and stiffness modulus: development, validation and numerical simulations”, Matéria (Rio de Janeiro), v. 27, n. 1, pp. e13130, 2022. doi: https://doi.org/10.1590/S1517-707620220001.1330.
    » https://doi.org/10.1590/S1517-707620220001.1330
  • [27]
    JABAR, A.B., PRADEEP, T., “ANN-PSO modelling for predicting bucking of self-compacting concrete column containing RHA properties”, Matéria (Rio de Janeiro), v. 28, n. 2, pp. e20230102, 2023. doi: https://doi.org/10.1590/1517-7076-RMAT-2023-0102.
    » https://doi.org/10.1590/1517-7076-RMAT-2023-0102
  • [28]
    ZHOU, X., XIE, J., ZHANG, M., “Numerical analysis of combined optimization of turbine runner flow pattern and shafting system”, Matéria (Rio de Janeiro), v. 27, n. 4, pp. e20220172, 2022. doi: https://doi.org/10.1590/1517-7076-RMAT-2022-0172.
    » https://doi.org/10.1590/1517-7076-RMAT-2022-0172
  • [29]
    SOUZA, L.A.F., VANALLI, L., VANDERLEI, R.D. et al, “Nonlinear numerical model of plane frames considering semi-rigid connection and different beam theories”, Matéria (Rio de Janeiro), v. 26, n. 3, pp. e13037, 2021. doi: https://doi.org/10.1590/S1517-707620210003.13037.
    » https://doi.org/10.1590/S1517-707620210003.13037
  • [30]
    SANTOS, R.A., MEIRA, G.R., BEZERRA, W.V.D.C., et al, “Use of numerical method for optimization of granulometric curves in eco-efficient concrete”, Matéria (Rio de Janeiro), v. 26, n. 4, pp. e13115, 2021. doi: https://doi.org/10.1590/S1517-707620210004.1315.
    » https://doi.org/10.1590/S1517-707620210004.1315

Publication Dates

  • Publication in this collection
    24 May 2024
  • Date of issue
    2024

History

  • Received