Acessibilidade / Reportar erro

An integrated pit-to-plant approach using technological models for strategic mine planning of copper and gold deposits

Abstract

The strategic mine plan is a crucial step for the success of mining companies, and for its development, it is necessary to use a number of inter-related variables that are usually estimated independently. These variables include operational data that is traditionally isolated in information islands between the different departments in the mine or they are consolidated into individual models. This reduces the holistic view of the deposit, thereby causing a negative impact on the results of the strategic planning itself. In order to improve the process and to maximize the production and/or value of a mining project, there needs to be an integration of the geology, the mine plan, the processing and the geometallurgy data. In order to accomplish this, a new methodology is proposed for the creation of a technological model. This model can be interpreted as the consolidation of the different models required for a better understanding of the geological and technical information of the deposit. This concept was developed and applied at a copper and gold mine site located in Brazil. Based on the evaluation of different blasting and mill productivity scenarios through a pit-to-plant approach, it was possible to obtain operational short-term gains such as a 10.7% increase in the plant production rate and a 2.2% increase in the crusher's feed rate with little or no capital investment.

keywords:
strategic planning; pit-to-plant; technological model; copper and gold; geometallurgy

1. Introduction

The strategic planning of a mine is a crucial step for the success of mining companies, since it provides the necessary information for the decision-making process concerning the development of the deposit (Silva, 2008SILVA, N. Metodologia de planejamento estratégico de lavra incorporando riscos e incertezas para a obtenção de resultados operacionais. 2008.). Therefore, in terms of strategic mine planning, it is important that the uncertainty related to the orebody is properly quantified, assessed, and managed (Godoy, 2018GODOY, M. A Risk analysis based framework for strategic mine planning and design - method and application. Advances in Applied Strategic Mine Planning, p. 75-90, 2018.). For the preparation of the strategic mine plan, it is necessary to use models and data that are often estimated independently.

The technological model presented in this manuscript, aims to solve the disconnected and many times, inaccurate view of the deposit. This new approach consolidates the different data used to gain a better understanding of the geological, mine planning and processing data of the project. Lund and Lamberg (2014)LUND, C., LAMBERG, P. Geometallurgy - a tool for better resource efficiency. European geologist, v.37, p. 39-43, 2014. state that the construction of technological models can reduce operational risks and could help to optimize the production, taking into account sustainability and socio-economic factors.

The data that is being referred to in this study includes the resource and structural models, the geometallurgical model, the cost model and the operating Selective Mining Unit (SMU) model, which is the smallest volume of material that the classification of ore and waste can be determined (Sinclair and Blackwell, 2002SINCLAIR, A., BLACKWELL, G. Applied mineral inventory estimation. United Kingdom: Cambridge University Press, 2002.).

The Geometallurgical model, a component of the technological model, allows for a better understanding of the ore characteristics. The importance of this increased knowledge base is that by knowing the strength, structure, and grade, there are adjustments that can be made to the crushing, grinding, and floatation processes (La Rosa et al., 2014LA ROSA, D., RAJAVUORI, L., KORTENIEMI, J., WORTLEY, M. Geometallurgical modelling and ore tracking at Kittila Mine. In: OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM, 2014.).

Gomes et al. (2016)GOMES, R. B., DE TOMI, G., ASSIS, P. A. Mine/Mill production planning based on a Geometallurgical Model. REM: Revista Escola de Minas, v. 69, n. 2, p. 213-218, 2016. used a geometallurgical model to support an economic study considering reserve volumes, product quality and operational cost. From the model a remarkable gain was obtained in the iron ore reserve and in an operation cost reduction. Its use is also essential for strategic mining planning for mines that seek to optimize the use of mining resources over the life of mine (Philander and Rozendaal, 2014PHILANDER, C., ROZENDAAL, A. A process mineralogy approach to geometallurgical model refinement for the Namakwa Sands heavy minerals operations, west coast of South Africa. Minerals Engineering, v. 65, p. 9-16, 2014.). Navarro et al. (2018)NAVARRA, A., GRAMMATIKOPOULOS, T., WATERS, K. Incorporation of geometallurgical modelling into long-term production planning. Minerals Engineergin, v. 120, p. 118-126, 2018. incorporated the geometallurgical modeling in long-term planning and confirmed its great impact on the life of mine.

As noted by Augustin et al. (2017)AUGUSTIN, M., BONKEKA, M., PATRICK, M. Strategic mine planning approach applied to large scale copper open pit mines by comparing the impact of three different bloc models of the same deposit, on the Long Term Mine Plan. International Journal of Advanced Research in Engineering, v. 3, n. 2, p. 1-5, 2017. the models should continually be updated whenever possible, by way of additional exploratory drill holes, to ensure that a greater detail of accuracy is achieved. Nadolski et al. (2015)NADOLSKI, S., KLEIN, B., ELMO, D., SCOBLE, M. Cave-to-mill: a mine-to-mill approach for block caves mines. Mining Technology, v.124, p. 47-55, 2015. complement that these models require constant adjustment, with the insertion of the geotechnical, geological, metallurgical and other operational data from the plant, which will also serve to calibrate predictive models.

The development process for the preparation of the technological model in question, used the work undertaken at a large-scale open pit copper and gold mine of sulfide ore located in Brazil, as a reference. The process includes crushing, grinding, and flotation. The saleable product is a copper-gold concentrate.

In the studied mine, the ore comes from different mining faces feeding the plant at the same time. The technological model created, tracked the ore characteristics back to its original mining face. One of the main objectives of the technological model was to determine the plant performance by the ore domain on an industrial scale and, to adjust the blasting parameters aiming to increase the plant throughput but keeping the metallurgical recoveries at similar or higher levels. This concept of pit-to-plant optimization has been in use at other mine sites around the world where different processes of integration and optimization were applied (Jankovic and Valery, 2011JANKOVIC, A., VALERY, W. New methodology to improve productivity of mining operations. In: BALKAN MINERAL PROCESSING CONGRESS, TURKEY, 14. v. 1, p. 557-565, 2011. (Conference).).

2. Materials and methods

As a starting point for the model, the different unit operations of the mine and plant were characterized. Blasting designs, mine and plant sampling, and operational testing were carried out. The data obtained was used to develop the specific models for the prediction processes of blasting, crushing, and grinding. These models were the basis of the construction of the technological model. Figure 1 summarizes the components of the technological model.

Figure 1
Components of the Technological Model

The methodology used for the preparation of the technological model is based on the following steps:

  • Characterization and delineation of areas based on their geological structure, strength, and correlation with their lithological and structural domains.

  • Establishing operating restrictions such as the stability of benches, the presence of water, SMU size, ore dilution allowance, the blast pile characteristics, the size of the equipment, and the size/power of the crushers/mills, in addition to any other bottlenecks in the process.

  • Defining the main requirements of the subsequent steps to plan for each geological domain in order to meet their specific requirements.

  • Use of software, mathematical models, and process simulation.

  • Implementation and monitoring of the defined operational strategy (suitable plans for each domain followed by the ideal adjustment for the crushing and grinding cycle).

  • Analysis and management of data and results.

  • Project implementation and maintaining the benefits obtained.

The above methodology is simplified in the Figure 2.

Figure 2
Project flow chart

The first step required an audit to be carried out during the drilling and blasting operations. This was necessary in order to obtain data, pictures, and other observations that are required to provide enough information for the creation of the fragmentation models. Once the information is obtained, the blasting techniques can be tailored to the rock characteristics, which will allow for substantial improvements in the downstream operations (Kanchibolta et al., 2015KANCHIBOTLA, S. S., VIZCARRA, T. G., MUSUNURI, S. A. R., TELLO, S., HAYES, A., MOYLAN, T. Mine to mill optmisation at paddington gold operations. In: INTERNATIONAL CONFERENCE ON SEMI-AUTOGENOUS AND HIGH PRESSURE GRINDING TECHNOLOGY, 2015.).

Simulations of the blasting plan were executed with both the soft and hard ore. Various parameters were changed depending on the simulation. Compared to the base case these variations included, a slight increase in bench height, an increase in hole diameter, a change in spacing, sub drilling, hole depth, stemming, and an increase in the column charge.

In the second phase of the preparation of the technological model, laboratory tests, image analyses, data processing, and mathematical models were consolidated. In order to optimize the ROM fragmentation from the mine blasting, a fragmentation model was developed. This model is sensitive to the main parameters that affect the blasting performance. The fragmentation model was then calibrated with the data obtained from the observed blasting during the audit process and used to predict changes in the particle size distribution of the ROM.

Fragmentation measurement using image analysis

Particle size distribution of the ROM is one of the parameters used in calibrating the fragmentation model. Prior studies of operations around the world have indicated that image analysis is a good and practical method for this purpose. Photographs of the piles formed after the verified blasting and primary crushing were processed using the Split-Desktop software (Split Engineering, 2017SPLIT ENGINEERING. Split-Desktop - Version 4.0. Retrieved from https://www.spliteng.com, 2017.
https://www.spliteng.com...
). Each image contains an object for scale. For this project, two Styrofoam balls were used and are pictured in Figure 3.

Figure 3
Example of a rendered image from the Split-Desktop software

Blast Tracking

Electronic tags were used to track the blasted material, enabling the verification of when the material enters the crushing/grinding cycle. Therefore, the complete sampling of the plant could be performed using the audited blasted material. Samples collected from the conveyor belts and the main streams for laboratory tests determined the breaking characteristics of the material. Specific models were developed for the blasting, crushing, grinding, and classification processes by using the audited blast data, sampling, and testing. Figure 4 shows the electronic tag with a diameter of 60mm and a height of 30mm used in the study as well as the typical installation of the electronic tag system with an antenna positioned above the conveyor belt.

Figure 4
The Reinforced Electronic Tag and the antenna above the conveyor belt

In total, 274 electronic tags were used in the survey data. They were put in the stem, in the piles formed after detonation, and in the feed of each primary crusher. In order to obtain the data for calibrating the mathematical models for the different equipment in the circuit, sampling was performed in the crushing and grinding circuit. Operational data was also collected during the sampling to determine the production rates and power consumption of each piece of equipment listed in Table 1. The sampling points are shown in the flowchart in Figure 5. Once the sampling was complete, the data was balanced and modelling was performed in the JKSimMet software (JKTech, 2014JKTech. JKSimMet - Version 6.0 Steady State Mineral Processing Simulator. Brisbane, 2014.).

Table 1
List of the circuit comminution equipment.

Figure 5
Sampling points in the grinding cycle. Mass balance and adjustment models

After the completion of the mass balancing, the mathematical models of all the processing units were calibrated according to the Anderson and Awachie model for the primary crushers in the JKSimMet software version 6.0 (JKTech, 2014JKTech. JKSimMet - Version 6.0 Steady State Mineral Processing Simulator. Brisbane, 2014.) and Whiten (Whiten and White, 1979WHITEN, W. J., WHITE, M. E. Modeling and simulation of high tonnage crushing plants. In: INTERNATIONAL MINERAL PROCESSING CONGRESS, 12. São Paulo, p. 148-158, 1979.). The objective was to model the grinding cycle at the time of sampling. The perfect blend model and the variable rate model were adjusted to the ball and SAG mills, respectively. The cyclones were adjusted using Nageswararao's model (Nageswararao, 1995NAGESWARARAO, K. A Generalised model for hydrocyclone classifiers. Proceedings of Australasian Institute of Mining and Metallurgy, v. 300, n. 2, p. 21, 1995.).

Using the balanced flow data, that includes the mass flow rate, the percentage of dry solids, and the particle size distribution, the models could be adjusted with respect to the parameters of each specific operation. Other information taken into account were the characteristics of the ore, the dimensions of the equipment, and the information related to the operation during sampling, which includes the load and speed levels of the mills, the energy consumption, and the operating pressure of the cyclones. Historical data was also considered to ensure that the results are consistent and that they represent the operation of the cycle as accurately as possible.

3. Test results and discussion

In total there were 24 blasting simulations carried out. Eleven of those simulations were performed on soft ore, and the remaining thirteen, which are shown below, were carried out on hard ore. Once the simulations were completed, one of the thirteen (base case) was selected to be applied to the blasting plan in the field. The hard ore simulations are presented in the Table 2 below.

Table 2
Blasting scenarios for hard ore.

The use of electronic tags in the blasted material proved to be effective in tracking the ore from the mine to the plant and assured that the audited blasted material was fed to the plant during sampling. During the 34-hour monitoring period, 131 electronic tags out of the 274 were detected. The spatial coordinates of each detected electronic tag are shown in Figure 6.

Figure 6
The positioning of each electronic tag detected

After the plant sampling was complete and the experimental data was collected, the model could be created. The mass balancing results compared well to the experimental data, indicating that the sampling data is valid for further analysis. In general, the models developed in JKSimMet (JKTech, 2014JKTech. JKSimMet - Version 6.0 Steady State Mineral Processing Simulator. Brisbane, 2014.) were well adjusted with respect to the data, and are considered appropriate for long-term simulation studies that are to be used in strategic mine planning. The experimental and modeled data can be compared in Table 3 below.

Table 3
Experimental and modeled data from the main streams.

The results of the rock blasting simulations demonstrated the importance of improving the results of fragmentation, especially when analyzing the productivity of an integrated comminution process for harder lithology. There was a 37% reduction in the production rate of the SAG (2026 to 1269 t/h) when the circuit supply consisted only of hard material. Under this same condition, increasing the powder factor to 2.78 kg/m3 resulted in an increase in the mill's productivity by 10.7%. This result directly relates to the finer particle size distribution obtained from the increased energy in the rocks from the blasting.

The SAG cycle improves with an increase in the load (the percent of mill volume occupied by media plus voids) from 8% mill balls (measured after grinding) to 10-13% mill balls. These changes allowed the grinding circuit to increase to within 2-4% of the productivity achieved with the largest open area. In order to better utilize the installed power of the pebble crushers, SAG mill grates with larger openings were installed. When comparing the scenario to the finer ROM, the simulation resulted in a 14% increase in pebble generation, while the feed rate increased by 2.2%. It is important to note that by increasing the opening of the grate, the grate life is shortened. Therefore, it was suggested to find alternatives in order to minimize the wear on the grate.

As an outcome of this methodology, the technological model has shown to be adherent to the plant results and operational data collected after many reconciliation processes. This methodology is still being used at the mine, which constantly updates the model with the new input data.

The results of the simulated scenarios with different mill loads are presented in Table 4.

Table 4
Simulated scenarios with the optimization of the SAG.

4. Conclusion

The methodology for the implementation of the technological model proved to be a viable option in this scenario, and has the potential to be applied to different projects with similar grinding processes. For the studied mine, the technological model which was an outcome of the assessment was incorporated into the short and medium term mine planning schedules. It was formulated as a block model and was used together with the mine planning software. The different technological variables presented in this model enabled the engineers to simulate different blasting and plant productivity scenarios, supporting the decision making process for the development of the deposit. As a result, it is possible to improve the efficiency of the plant with little or no capital investment by optimizing the breaking and fragmenting mechanisms through blasting, crushing, and grinding. This resulted in:

  • A reduction of the top size of the ROM, which allowed the primary crusher to operate with a higher feed rate by 2.2%, a reduced opening, and to feed the SAG with a smaller top size.

  • Operating the SAG with more fines (<10mm) by increasing the powder factor to 2.78kg/m3, increased the plant production rate by 10.7% while using the same power.

References

  • AUGUSTIN, M., BONKEKA, M., PATRICK, M. Strategic mine planning approach applied to large scale copper open pit mines by comparing the impact of three different bloc models of the same deposit, on the Long Term Mine Plan. International Journal of Advanced Research in Engineering, v. 3, n. 2, p. 1-5, 2017.
  • GODOY, M. A Risk analysis based framework for strategic mine planning and design - method and application. Advances in Applied Strategic Mine Planning, p. 75-90, 2018.
  • GOMES, R. B., DE TOMI, G., ASSIS, P. A. Mine/Mill production planning based on a Geometallurgical Model. REM: Revista Escola de Minas, v. 69, n. 2, p. 213-218, 2016.
  • JANKOVIC, A., VALERY, W. New methodology to improve productivity of mining operations. In: BALKAN MINERAL PROCESSING CONGRESS, TURKEY, 14. v. 1, p. 557-565, 2011. (Conference).
  • JKTech. JKSimMet - Version 6.0 Steady State Mineral Processing Simulator. Brisbane, 2014.
  • KANCHIBOTLA, S. S., VIZCARRA, T. G., MUSUNURI, S. A. R., TELLO, S., HAYES, A., MOYLAN, T. Mine to mill optmisation at paddington gold operations. In: INTERNATIONAL CONFERENCE ON SEMI-AUTOGENOUS AND HIGH PRESSURE GRINDING TECHNOLOGY, 2015.
  • NADOLSKI, S., KLEIN, B., ELMO, D., SCOBLE, M. Cave-to-mill: a mine-to-mill approach for block caves mines. Mining Technology, v.124, p. 47-55, 2015.
  • NAVARRA, A., GRAMMATIKOPOULOS, T., WATERS, K. Incorporation of geometallurgical modelling into long-term production planning. Minerals Engineergin, v. 120, p. 118-126, 2018.
  • LA ROSA, D., RAJAVUORI, L., KORTENIEMI, J., WORTLEY, M. Geometallurgical modelling and ore tracking at Kittila Mine. In: OREBODY MODELLING AND STRATEGIC MINE PLANNING SYMPOSIUM, 2014.
  • LUND, C., LAMBERG, P. Geometallurgy - a tool for better resource efficiency. European geologist, v.37, p. 39-43, 2014.
  • NAGESWARARAO, K. A Generalised model for hydrocyclone classifiers. Proceedings of Australasian Institute of Mining and Metallurgy, v. 300, n. 2, p. 21, 1995.
  • PHILANDER, C., ROZENDAAL, A. A process mineralogy approach to geometallurgical model refinement for the Namakwa Sands heavy minerals operations, west coast of South Africa. Minerals Engineering, v. 65, p. 9-16, 2014.
  • SILVA, N. Metodologia de planejamento estratégico de lavra incorporando riscos e incertezas para a obtenção de resultados operacionais 2008.
  • SINCLAIR, A., BLACKWELL, G. Applied mineral inventory estimation United Kingdom: Cambridge University Press, 2002.
  • SPLIT ENGINEERING. Split-Desktop - Version 4.0. Retrieved from https://www.spliteng.com, 2017.
    » https://www.spliteng.com
  • WHITEN, W. J., WHITE, M. E. Modeling and simulation of high tonnage crushing plants. In: INTERNATIONAL MINERAL PROCESSING CONGRESS, 12. São Paulo, p. 148-158, 1979.

Publication Dates

  • Publication in this collection
    Apr-Jun 2019

History

  • Received
    02 May 2018
  • Accepted
    19 Nov 2018
Fundação Gorceix Rua Carlos Walter Marinho Campos, 56, Cep: 35400-000, Tel: (31) 3551-4730 - Ouro Preto - MG - Brazil
E-mail: editor@rem.com.br